The Substation
The AI buildout isn't short of money or chips. It's short of megawatts with a delivery date. The contracts signed in the past twenty months, the interconnection queues, and the turbine order books all say the same thing, and they say it in numbers that are easier to read than the capex.
- 474 GWof large-load requests in the Texas interconnection queue in August 2026, more than five times the grid's record peak
- $333/MW-dayPJM capacity price for 2027/28, at the regulatory cap for the second year running
- 116 GWGE Vernova's gas turbine backlog and reservations, with slots now being sold for 2031 delivery
- 1.2%of announced behind-the-meter data center generation that was actually under construction by mid-2026
In the first seven months of 2026, data centers accounted for about 9% of the wholesale cost of power across PJM, the grid that serves 65 million people from Chicago to Washington. That's $10.48 of a $116.53 per megawatt-hour average, and the average itself was up 46% on the year.6 The same market monitor attributes $29.4 billion of the last four capacity auctions, 46% of the total, to existing and forecast data center load.5 Those two numbers are the cleanest measurement anyone has produced of what the AI buildout costs a grid, and they come from the grid's own referee.
The first two analyses on this site were about capital: who's spending it and whose name is on it. This one is about the thing capital can't buy on a schedule. A gigawatt of compute needs a gigawatt of firm supply, a substation to land it, and a turbine or a reactor behind it, and each of those has a queue. Read the buildout through the queues and it looks different from the way it looks through the capex.
The contracts
Start with what's been signed. The hyperscalers have contracted about 4.5 gigawatts of nuclear capacity in five deals, three of them restarts or relicensings of reactors that were closed or about to close.1 None of the prices are public. Analysts put the Microsoft and Meta contracts somewhere between $70 and $115 per megawatt-hour, which is a premium of roughly $20 to $40 over the local wholesale price, and Constellation has since guided $80 to $88 for future front-of-meter deals.15
Nuclear capacity contracted by hyperscalers, 2024 to 2026
Megawatts · term length in the note · prices undisclosed in every case
| Deal | Signed | MW | Status |
|---|---|---|---|
| Amazon, Talen Susquehanna | Jun 2025 | 1,920 | Front-of-meter PPA through 2042 after FERC rejected the behind-the-meter expansion in Nov 2024. Ramps from 2029. |
| Meta, Constellation Clinton | Jun 2025 | 1,121 | 20 years from June 2027, when the Illinois subsidy expires. Includes relicensing and a 30 MW uprate. |
| Microsoft, Constellation Crane | Sep 2024 | 835 | Three Mile Island Unit 1 restart. FERC waiver in Jun 2026 moved restart to H2 2027, a year early. |
| Google, NextEra Duane Arnold | Oct 2025 | 615 | 25-year PPA. DOE loan of up to $1.9B closed Sep 2026. Restart late 2028. |
| Google, Kairos Hermes 2 | Aug 2025 | 50 | First binding PPA for a US advanced reactor, via TVA. Operations targeted 2030. |
Two things about the nuclear deals matter more than their size. The first is timing. The earliest of them delivers in the second half of 2027 and the largest doesn't reach full quantity until 2032, so none of this power serves the capacity being built with this year's $800 billion.12 The second is the regulator. Amazon's original plan was to take Susquehanna's output behind the meter, off the grid entirely. FERC rejected the expansion in November 2024, opened a proceeding on co-location in February 2025, and in December ordered PJM to write rules for it. The deal that survived is a conventional front-of-meter contract, which means the load shows up in everyone's grid.216
The near-term capacity is gas, and much of it is being built on site to avoid the queue. Crusoe secured 4.5 gigawatts of gas-fired supply for the Abilene campus where Oracle serves OpenAI. Oracle's second Texas site runs on a 700 megawatt microgrid of 210 gas gensets. xAI's Memphis and Southaven campuses run on dozens of mobile turbines, and the second site is the subject of a Clean Air Act suit over 27 unpermitted units, in which the Justice Department intervened on xAI's side citing national security.78 Cleanview counts about 90 gigawatts of behind-the-meter generation announced for data centers by mid-2026, 92% of it since January 2025. About 1.1 gigawatts, or 1.2%, was under construction.30
The queue
The interconnection queue is where announced and real get sorted, and the Texas one has become the clearest instrument in the country. Large-load requests in ERCOT stood at about 233 gigawatts at the end of 2025, up roughly 300% in a year, with more than 70% from data centers.10 By March the chief executive told the state senate it was 410 gigawatts, 87% data centers.11 By August it was about 474 gigawatts, over five times the system's record peak demand, and the governor ordered every project audited before any could advance.12
Large-load requests in the ERCOT interconnection queue
Gigawatts · share from data centers in the note
Texas has responded the way a market does when a queue stops meaning anything: it started charging to be in it. The utility commission now requires $50,000 per megawatt of financial security to hold a place, most of it non-refundable, and from this year only loads with signed interconnection agreements count in the forecast.11 Senate Bill 6, signed in June 2025, lets the grid operator curtail any new large load during a shortage.13 Britain's regulator proposed the same thing in July: commitment fees of £237,500 to £712,500 per megawatt for data centers that want to keep a grid slot, after the connection queue reached 738 gigawatts against 200 to 225 needed.3233
PJM has no queue fee; it has a price. Its capacity auction cleared at $329.17 per megawatt-day for 2026/27, the regulatory cap and up 22% on the year, and at $333.44 for 2027/28, the cap again, with the market 6.6 gigawatts short of its reliability requirement.34 PJM's own forecast attributes 30 of the 32 gigawatts of peak growth it expects by 2030 to data centers, and its ten-year growth rate has gone from 0.3% a year in the 2021 forecast to 3.6% in this year's.1415 An uncapped auction, by PJM's own simulation, would have cleared near $389.3
Who pays
A study published in May by North Carolina State, Carnegie Mellon, Pittsburgh, and Toronto projects retail electricity prices rising 6% to 29% nationally by 2030 because of data center load, and up to 57% in the most exposed regions, which are exactly the ones on the ledger: Virginia, Pennsylvania, Ohio, west Texas.20 The industry's own consultant, E3, working for the Data Center Coalition, attributes about half of the PJM capacity price increase between the 2024/25 and 2025/26 auctions to load growth and the other half to market design and retirements, and finds no evidence of historical cross-subsidy.21 Both can be true. The question regulators are actually deciding isn't whether data centers raised prices in the past. It's who carries the fixed cost of the plants being built for them now.
| Jurisdiction | Rule | Terms |
|---|---|---|
| Ohio, AEP | Data center tariff, Jul 2025 | Loads over 25 MW pay for at least 85% of contracted demand whether or not they use it, for up to 12 years. Exit fee equals three years of minimum charges.17 |
| Virginia, Dominion | GS-5 rate class, Nov 2025 | 14-year contracts for loads of 25 MW and up; minimum 85% of contracted delivery demand and 60% of generation demand; collateral; three years' notice to reduce load. Effective January 2027.18 |
| Georgia | Large-load rules, Jan and Dec 2025 | Bespoke contracts above 100 MW with upfront payments and guarantees. The commission certified 9,885 MW of new generation in December, about $16.5B, roughly 90% of it for data centers.19 |
| Texas | Senate Bill 6, Jun 2025 | Mandatory curtailment of new large loads during firm load shed; disclosure, site-control, and financial-commitment standards; $50,000 per MW queue security.1311 |
| Federal | Ratepayer Protection Pledge, Mar 2026 | Seven companies pledge to build, bring, or buy their own generation and pay for delivery upgrades. Non-binding, with no enforcement mechanism.9 |
Notice the shape these rules share. They don't cap data center demand. They convert it into a take-or-pay contract: a minimum bill, a long term, collateral, an exit fee. That's the structure of a project-finance offtake agreement, and it's being written into utility tariffs because regulators have concluded the announced load can't be trusted at face value. Dominion has 51 gigawatts of data center capacity under contract, Southern has 10 gigawatts fully contracted against a 75 gigawatt pipeline, and AEP raised its five-year capital plan to $78 billion on the strength of signed load.222324 Every one of those numbers is now backed by a minimum-bill tariff, which is the difference between a forecast and a receivable.
The turbine
Behind every queue is a physical order book, and it's the most concrete forward indicator the buildout has. GE Vernova ended the second quarter with 116 gigawatts of gas turbine backlog and reservations, up from 100 in the first quarter, and is now taking reservations for 2031 delivery. Its production target is 20 gigawatts a year this quarter, rising to 30 by 2030.25 Siemens Energy holds 69 gigawatts with lead times over three years. Mitsubishi Power holds 35, up from 23 a year earlier, and is sold out through 2028.2627
Gas turbine backlogs at the three largest makers, mid-2026
Gigawatts · backlog plus reservations where the maker reports both
Prices followed. BloombergNEF puts the average combined-cycle project at $2,157 per kilowatt in 2025 against under $1,500 in 2023, and Wood Mackenzie expects the turbine alone to reach about $600 per kilowatt by the end of 2027, nearly triple 2019.25 Transformers are worse: 128 weeks average for a power transformer, 144 for a generator step-up unit, up to four years for the largest.28 Global Energy Monitor counts 189 gigawatts of US gas capacity in development tied to data centers as of mid-2026, nearly double the figure six months earlier, with 77 of it in Texas.29 Bloomberg's analysis of 99 proposed behind-the-meter plants puts their emissions at about 318 million tonnes a year if run at industry-standard rates, a fifth of the entire US power sector's 2025 output.31
Put the three sections together and the buildout has a clock that the capex figures don't show. The nuclear deals deliver from late 2027. Turbine slots ordered today deliver in 2029 to 2031. Transformers take two to four years. Queues in Texas and Britain are being audited and priced because most of what's in them won't be built. Whatever the five companies' 2026 spending buys, the power to run it at scale is a 2028 to 2032 event, and the contracts say so in writing.
So when the next data center announcement arrives, the number to find isn't the dollars or the gigawatts of compute. It's three other things. Whether the power is behind the meter or grid-served, because that decides which regulator and which lawsuit. Whether there's a signed interconnection agreement and a tariff with a minimum bill, because that's what separates a receivable from a press release. And the delivery year on the turbine or reactor, because that's the date the project actually starts.
Method
Contract capacities are from the counterparties' own releases or filings. Prices are undisclosed in every nuclear deal; analyst estimates are quoted as estimates and excluded from charts. Interconnection queue figures are from ERCOT's own testimony and regulator filings and count requests, not committed projects. PJM figures are from PJM auction reports, its 2026 load forecast, and the Independent Market Monitor. Utility capital plans and contracted load are from company releases and earnings coverage. Turbine backlogs are as reported by each manufacturer; GE Vernova's figure includes slot reservations. Behind-the-meter counts from Cleanview and Global Energy Monitor are compiled datasets and are marked as such. The Talen implied price and the Stargate UAE power mix were excluded as unverifiable. Nothing here is investment advice.
Sources
- 1Constellation Energy, Crane Clean Energy Center; Utility Dive on the FERC waiver, Jun 2026. utilitydive.com
- 2Talen Energy, 8-K press release on the Amazon PPA, 11 Jun 2025. sec.gov
- 3PJM, 2026/2027 Base Residual Auction report, 22 Jul 2025. pjm.com
- 4PJM, 2027/2028 Base Residual Auction report, 17 Dec 2025. pjm.com
- 5PJM Independent Market Monitor on data center share of capacity cost, via Utility Dive, 20 Jul 2026. utilitydive.com
- 5bConstellation, Meta 20-year Clinton agreement, 3 Jun 2025; Utility Dive on analyst pricing. constellationenergy.com
- 6PJM Independent Market Monitor, data center share of wholesale cost, Jan to Jul 2026, via Utility Dive, 27 Aug 2026. utilitydive.com
- 7Data Center Frontier, Crusoe 4.5 GW gas supply for Abilene, Mar 2025. datacenterfrontier.com
- 8Utility Dive, DOJ intervenes in xAI turbine lawsuit, Jul 2026. utilitydive.com
- 9White House, Ratepayer Protection Pledge fact sheet, 4 Mar 2026. whitehouse.gov
- 10Utility Dive, ERCOT large-load queue up almost 300% in 2025, 6 Jan 2026. utilitydive.com
- 11ERCOT, large-load update to the Texas Senate, 1 Apr 2026. ercot.com
- 12Akin Gump, Texas pauses data center interconnections pending audit, Aug 2026. akingump.com
- 13McGuireWoods, Texas Senate Bill 6 summary, Jul 2025. mcguirewoods.com
- 14PJM 2025 long-term load forecast, data center share of peak growth, via DCD, Jan 2025. datacenterdynamics.com
- 15PJM, 2026 Long-Term Load Forecast Report, 14 Jan 2026. pjm.com
- 16FERC, order directing PJM to create co-location rules, 18 Dec 2025. ferc.gov
- 17PUCO, AEP Ohio data center tariff order, 9 Jul 2025. puco.ohio.gov
- 18Virginia SCC, Dominion biennial review order including the GS-5 class, 25 Nov 2025. scc.virginia.gov
- 19Georgia PSC, data center fact sheet and Dec 2025 certification. psc.ga.gov
- 20NC State University, data center effect on retail power prices by 2030, Environmental Research Letters, 12 May 2026. news.ncsu.edu
- 21E3 for the Data Center Coalition, drivers of rising electricity rates, May 2026. ethree.com
- 22Utility Dive, NextEra and Dominion merger and contracted data center capacity, 18 May 2026. utilitydive.com
- 23Utility Dive, Southern Company capital plan and contracted load, 20 Feb 2026. utilitydive.com
- 24AEP, capital plan update, 2026. aep.com
- 25Utility Dive, GE Vernova gas turbine backlog reaches 116 GW, with turbine price estimates, 22 Jul 2026. utilitydive.com
- 26Utility Dive, Siemens Energy backlog near 70 GW, Aug 2026. utilitydive.com
- 27Utility Dive, Mitsubishi Power backlog, 6 Aug 2026. utilitydive.com
- 28pv magazine, Wood Mackenzie transformer lead-time survey, 11 May 2026. pv-magazine-usa.com
- 29Global Energy Monitor, US gas proposals tied to data centers nearly double in six months, Aug 2026. globalenergymonitor.org
- 30Cleanview, behind-the-meter data center power tracker, mid-2026. cleanview.co
- 31Bloomberg, data center gas plants to boost US power emissions by 20%, 18 Aug 2026. bloomberg.com
- 32Ofgem, commitment fees to free grid capacity from speculative data centre projects, 29 Jul 2026. ofgem.gov.uk
- 33NESO, connections reform results, Dec 2025. neso.energy
- 34EIA, Short-Term Energy Outlook, Aug 2026. eia.gov
Cite this
Wisniewski, K. (2026, September 11). The Substation. Institutional AI Investment, kylewisniewski.com. https://www.kylewisniewski.com/institutional-ai/analysis/the-substation